Bond 2023 Progress Update: March 2024

We extend our heartfelt gratitude for your invaluable support in passing the 2023 Bond! This measure holds immense significance for our district, and we deeply appreciate the unwavering backing of our community in bringing it to fruition. In our inaugural video progress update, we paid a visit to Eight Mile Stadium, the focal point of current activity, where construction crews are diligently dismantling the home and visitor bleachers. This undertaking holds particular significance within the bond, as the replacement bleachers will be fully ADA compliant, equipped with handrails, and accommodating 4,500 seats.
Show Transcript
Thank you to our community for their support in passing the 2023 Bond, which is enabling crucial improvements throughout our district. The bond will enhance our schools and expand our capacity to provide top-tier education.
 
Progress updates include the demolition of bleachers at Eight Mile Stadium, ongoing design work for Amerman's addition and renovation, and the commencement of design work for district-wide LED lighting upgrades.
 
Additionally, contracts for the NHS baseball and softball turf project have been sent out, and planning for Meads Mill's addition and renovation is underway. Installation of playgrounds at Moraine, Silver Springs, and Winchester is scheduled for summer 2024, along with roofing projects at various locations. Technology initiatives include the completion of the Wireless Access Point project and upgrades to the district's fiber optic network.
 
In our inaugural video progress update, we paid a visit to Eight Mile Stadium, the focal point of current activity, where construction crews are diligently dismantling the home and visitor bleachers. This undertaking holds particular significance within the bond, as the replacement bleachers will be fully ADA compliant, equipped with handrails, and accommodating 4,500 seats.
 
For more information and progress updates, visit the district's Bond 2023 webpage
 
 
 
 
Here's a breakdown of the current projects going on:
 

Status Update: March 2024

  • Eight Mile Stadium
    • Demolition of the existing home and visitor bleachers has begun. Sitework and electrical work will continue on site in preparation of foundations for the new bleachers later this spring.
  • Amerman Addition and Renovation
    • Design team is working on an updated set of drawings that the construction company (Auch) will provide an estimate for. Over the next several months will be discussions over the design and bidding out the project.
    • Picture: Amerman Addition and Renovation rendering
  • NHS HVAC    
    • Design development drawings issued, project bidding will take place late 2nd quarter of 2024.
    • NHS Kitchen Make Up Air Unit installation scheduled for Summer 2024.
  • District-wide LED Lighting Upgrade
    • Design work complete at Amerman, Moraine, Ridge Wood, Silver Springs, Thornton Creek, Winchester, and NHS.
    • Construction will begin late 2024, anticipated completion will be the end of 2025.
    • Lighting upgrade at Meads Mill will be designed and performed with the Meads Mill renovation project.
  • NHS Baseball and Softball Fields
    • Contracts for the NHS baseball and softball turf project have been sent out.
    • Final storm water permit anticipated in 2nd quarter of 2024.
    • Construction to start late June 2024, with substantial completion end of 2024.
  • Meads Mill Addition and Renovation
  • 2024 Playgrounds: Moraine, Silver Springs, Winchester
    • Contracts have been sent out and design refinements are ongoing with building teams and vendors.
    • Installation planned for Summer 2024.
    • Picture: Playground rendering
  • 2024 Roofing
    • Technology & Operations roofing scheduled for Spring 2024.
    • NHS and Amerman roofing scheduled for Summer 2024.
  • Technology
    • Wireless Access Point project wrapping up.
    • District-wide fiber optic network upgrade out for bid.
    • Orders have been placed for district printer replacements and chromebook devices.